November 20, 2026
The National Energy Commission (Comisión Nacional de Energía, the “CNE”) published in the Federal Official Gazette (Official Journal of the Federation) the General Administrative Provisions governing the commercialization of natural gas, petroleum products, liquefied petroleum gas (“LPG”) and petrochemicals (the “Provisions”), establishing requirements for commercialization permits, contractual obligations, product traceability and regulatory reporting.
Below are the key points of the Provisions:
I. Commercialization Permits.
- Individual permits are required for natural gas, petroleum products, LPG and petrochemicals.
- Applicants must provide corporate information, supplier and customer letters of intent, demand projections, logistics arrangements and supporting documentation.
- New permits may be granted for up to two years. Continued operations after expiration require a new permit.
- Producers obtaining commercialization permits for products derived from their operations may not acquire third-party products for resale, unless expressly authorized.
- Newly issued permits must provide for expiration if no formal commercial offer is evidenced within 180 calendar days following issuance or the last commercial transaction, subject to CNE’s determination.
- Permit holders must notify CNE at least 20 business days before commencing operations and obtain approval of their contract model
II. Commercialization Obligations.
- Permit holders must substantiate the lawful origin and availability of products through applicable permits, agreements, invoices and supporting records.
- Permit holders must verify applicable authorizations before commercial transactions.
- Permit transfers, mergers and spin-offs require CNE authorization. Changes of corporate control require a permit update
- New permit holders face restrictions on transactions with other marketers based on transportation, storage, distribution and value-added services, subject to regulatory exceptions.
- Weekly operational information, quarterly transaction documentation and annual cost reports must be submitted to CNE, as applicable.
III. Commercial Agreements.
- Agreements must address product origin, traceability, volumes, delivery, quality, pricing, measurement and termination.
- Supplier and customer agreements must be registered through CNE’s Electronic Filing Office (“OPE”) within 10 business days following each semester.
- Contract amendments must be registered within five business days. Early termination or expiration within 10 business days.
- Reported transactions must be linked to registered agreements through a unique contract identifier (ContratoId).
IV. Transitional Provisions.
- Remain valid, but holders must comply with applicable requirements under the Provisions.
- 90 calendar days from November 5, 2026, to implement OPE registration and reporting systems.
- 30 business days from November 6, 2026, to submit outstanding contracts, demand, logistics and product origin information.
- 30 business days from November 6, 2026, to notify CNE of transportation or storage permits held within the same economic interest group, where required.
- 180 calendar days from November 6, 2026, to document product sourcing capacity and logistics arrangements.
- CNE must publish its model within 180 calendar days from November 6, 2026. Previously submitted or approved models remain valid.
The attorneys in our Energy and Infrastructure practice are available for any questions or comments regarding these Provisions.